Since Chongqing Zhonghui-First City project company was set up,we have been given the support from the company and city leaders at all levels and it helps the smooth progress of the project, which is completed all preparations for the sale.
The Sales Center project has been completed, outdoor landscape garden has been completed 90%.


11-13 # floor of the main structure has been capped, ongoing the masonry structure and equipment installation. # 22 of the mainstructure has reached level 4, House # 14 has been completed the hanging work of level 1 and 2; and the based construction of 16 # 15 and # 19-21 have been completed. 8-10 # is to be started the construction operation by the end of August 2008 due to the site reasons.

Construction of # 5 is up to level 20 ; # 6, construction to level 9, # 7 and# 29, the main structure of the garage were capped. The project is expected to be available by the end of September 2008 for sale.